Blackrod

Project Blackrod
Operator BlackPearl Resources Inc.
Ownership BlackPearl Resources Inc. 100%
Location 02-36-076-18W4
Technology SAGD
Bitumen Capacity (bbls/day) 800
Bitumen production rates (bbl/d) 2013
January – December
227
Bitumen production rates (bbl/d) 2012 269
Bitumen production rates (bbl/d) 2011 113
Number of wells actually producing or injecting/capable of production or injection 2013
January – December
2/2
Number of wells actually producing or injecting/capable of production or injection 2012 1/1
Number of wells actually producing or injecting/capable of production or injection 2011 1/1
Steam injection rates (bbl/d) 2013
January – December
1,252
Steam injection rates (bbl/d) 2012 1,132
Steam injection rates (bbl/d) 2011 292
Steam to oil ratio 2013
January – December
11.42
Steam to oil ratio 2012 4.42
Steam to oil ratio 2011 11.59
Water production rates (bbl/d) 2013
January – December
1,400
Water production rates (bbl/d) 2012 1,307
Water production rates (bbl/d) 2011 810
Water to steam ratio 2013
January – December
1.11
Water to steam ratio 2012 1.26
Water to steam ratio 2011 6.60

Project location and leases in close vicinity

(neighbouring leases may be owned by the operator, a partner, or competitor. Click on lease for details.)

BlackPearl says that it has been steaming the second pilot well pair since November with expectations to convert this well pair to SAGD operation in March. The company is testing a commercial well design after incorporating learning's from the first pilot well pair.

Operating phases

Phase Start Year Capacity Status
Pilot 2011 800 Operating

Future phases

Phase Start Year Capacity Status
Phase 1 2015 20,000 Application
Phase 2 2018 30,000 Application
Phase 3 2021 30,000 Application