Blackrod

Project Blackrod
Operator BlackPearl Resources Inc.
Ownership BlackPearl Resources Inc. 100%
Location 02-36-076-18W4
Technology SAGD
Bitumen Capacity (bbls/day) 800
Bitumen production rates (bbl/d) 2015
Jan - May
501
Bitumen production rates (bbl/d) 2014 399
Bitumen production rates (bbl/d) 2013 227
Number of wells actually producing or injecting/capable of production or injection 2015
Jan - May
3/3
Number of wells actually producing or injecting/capable of production or injection 2014 3/3
Number of wells actually producing or injecting/capable of production or injection 2013 2/2
Steam injection rates (bbl/d) 2015
Jan - May
850
Steam injection rates (bbl/d) 2014 1,212
Steam injection rates (bbl/d) 2013 1,252
Steam to oil ratio 2015
Jan - May
1.72
Steam to oil ratio 2014 3.51
Steam to oil ratio 2013 11.42
Water production rates (bbl/d) 2015
Jan - May
2,005
Water production rates (bbl/d) 2014 1,970
Water production rates (bbl/d) 2013 1,400
Water to steam ratio 2015
Jan - May
2.52
Water to steam ratio 2014 1.65
Water to steam ratio 2013 1.11

Project location and leases in close vicinity

(neighbouring leases may be owned by the operator, a partner, or competitor. Click on lease for details.)

BlackPearl reports that Production is expected to ramp-up to peak rates in 2015. During the first quarter of 2015, the pilot wells produced an average of 406 bbls/d of bitumen.

Operating phases

Phase Start Year Capacity Status
Pilot 2011 800 Operating

Future phases

Phase Start Year Capacity Status
Phase 1 TBD 20,000 Application
Phase 2 TBD 30,000 Application
Phase 3 TBD 30,000 Application