Blackrod

Project Blackrod
Operator BlackPearl Resources Inc.
Ownership BlackPearl Resources Inc. 100%
Location 02-36-076-18W4
Technology SAGD
Bitumen Capacity (bbls/day) 800
Bitumen production rates (bbl/d) 2014
Jan - Oct
377
Bitumen production rates (bbl/d) 2013 227
Bitumen production rates (bbl/d) 2012 269
Number of wells actually producing or injecting/capable of production or injection 2014
Jan - Oct
3/3
Number of wells actually producing or injecting/capable of production or injection 2013 2/2
Number of wells actually producing or injecting/capable of production or injection 2012 1/1
Steam injection rates (bbl/d) 2014
Jan - Oct
1,239
Steam injection rates (bbl/d) 2013 1,252
Steam injection rates (bbl/d) 2012 1,132
Steam to oil ratio 2014
Jan - Oct
3.78
Steam to oil ratio 2013 11.42
Steam to oil ratio 2012 4.42
Water production rates (bbl/d) 2014
Jan - Oct
1,962
Water production rates (bbl/d) 2013 1,400
Water production rates (bbl/d) 2012 1,307
Water to steam ratio 2014
Jan - Oct
1.60
Water to steam ratio 2013 1.11
Water to steam ratio 2012 1.26

Project location and leases in close vicinity

(neighbouring leases may be owned by the operator, a partner, or competitor. Click on lease for details.)

Production continues to ramp-up from the second pilot well pair at Blackrod. The well pair has produced over 50,000 barrels of oil since March 2014 and during the third quarter production from the second well pair averaged 316 barrels of oil per day with a steam oil ratio of approximately 3.3:1. Recent oil analysis from the well indicates the well pair is still in the early stages of steam chamber development. It is expected to reach target peak production of 500 to 600 barrels of oil per day in the next six to nine months.

Operating phases

Phase Start Year Capacity Status
Pilot 2011 800 Operating

Future phases

Phase Start Year Capacity Status
Phase 1 TBD 20,000 Application
Phase 2 2018 30,000 Application
Phase 3 2021 30,000 Application