Fort Hills

Project Fort Hills
Operator Suncor Energy Inc.
Ownership Suncor Energy Inc. 40.80%
Total E&P Canada Ltd. 39.20%
Teck Resources Limited 20%
Location 16-09-097-10W4
Technology Surface Mining

Project location and leases in close vicinity

(neighbouring leases may be owned by the operator, a partner, or competitor. Click on lease for details.)

Project activities in 2015 are expected to focus on completion of detailed engineering and continued ramp up of procurement and construction across all areas.

Future phases

Phase Start Year Capacity Status
Phase 1 - Mining 2017 160,000 Construction
Debottleneck TBD 20,000 Approved
Phase 1 - Upgrader TBD 145,000 Cancelled
Phase 2 & 3 TBD 145,000 Cancelled