Joslyn North Mine

Project Joslyn North Mine
Operator Total E&P Canada Ltd.
Ownership Occidental Petroleum Corporation 15%
Suncor Energy Inc. 36.75%
Total E&P Canada Ltd. 38.25%
Inpex Canada Limited 10%
Location 07-31-095-11W4
Technology Surface Mining

Project location and leases in close vicinity

(neighbouring leases may be owned by the operator, a partner, or competitor. Click on lease for details.)

Total has announced it will delay the Joslyn mine while project owners seek ways to reduce costs.

Future phases

Phase Start Year Capacity Status
Phase 1 2019 100,000 On Hold